How Much Gravel for a 150 Foot French Drain?

A 150 ft French drain in a trench 12 in wide and 18 in deep takes about 8.6 cubic yards (12.1 tons) of drain rock, with a 4 in pipe and 10% extra. You also need 150 ft of perforated pipe and 750 sq ft of filter fabric, and you will dig out 8.3 cubic yards of soil.

Jump to your result ↓

Your project

%

Uneven trench walls and settling.

Results

Example job shown. Change the numbers to match yours.

Drain rock needed
12.1 tons
Clean washed stone, 3/4 to 1½ in
Drain rock, cubic yards
8.63 yd³

Pipe and fabric

Perforated pipe
150 linear ft
10 ft pipe sections
15 pieces
Filter fabric (wraps the stone, with overlap)
750 ft²

Digging

Soil to dig out
8.3 yd³
  • Lay the pipe with the holes down, on a bed of stone, sloping at least 1 percent (about 1/8 in per foot) to a daylight outlet or a dry well. Wrap the stone in non-woven filter fabric to keep soil out. Soil is bulkier once it is dug, so the pile to haul away is bigger than the soil to dig out: allow extra and ask your hauler.

Before you buy: round up to whole packs, check the size printed on the label, and add a little spare. Your supplier has the final say.

Blueprint

150 ft1 ft18 in

8.63 yd³ gravel

What a 150 ft French drain takes

ItemAmount
Drain rock (clean washed stone, 3/4 to 1½ in)8.63 cubic yards, 12.1 tons
Perforated pipe, 4 in150 ft (15 pieces of 10 ft)
Non-woven filter fabric750 sq ft
Soil to dig out8.3 cubic yards

For a trench 12 in wide and 18 in deep, with 10% extra stone for uneven trench walls and settling. The stone is the trench volume less the space the pipe takes up, at 1.4 tons per cubic yard.

150 ft of drain, by trench size

Width × depth of the trench, with a 4 in pipe and 10% extra stone.

TrenchDrain rock, cubic yardsTonsFabric, sq ftSoil dug out, cubic yards
8 × 12 in3.545.05503.7
12 × 12 in5.587.86005.6
12 × 18 in8.6312.17508.3
12 × 24 in11.6916.490011.1
18 × 24 in17.8024.997516.7

A narrower trench saves stone on a long run

Over 150 ft the width of the trench is worth thinking about. At 18 in deep, a trench 8 in wide takes 5.6 cubic yards (7.8 tons), 12 in wide 8.6 cubic yards (12.1 tons) and 18 in wide 13.2 cubic yards (18.5 tons).

Every inch of width you do not dig is stone you do not buy. The trench still has to be wide enough to bed a 4 in pipe with stone on both sides.

Use clean, washed stone with no fines, wrap the stone (not the pipe) in the fabric, and make sure the drain has an outlet. The fittings, tools and steps are in the French drain materials list, and the method behind the stone figure is in how much gravel for a French drain.

Want to change anything else? The calculator above is the full French Drain Calculator: edit any number and the results update instantly.

Tools & materials for this project

Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.

Frequently asked questions

How much gravel do I need for a 150 foot French drain?

About 8.6 cubic yards, or 12.1 tons, of clean drain rock for a trench 12 in wide and 18 in deep with a 4 in pipe, including 10% extra. A 12 by 24 in trench takes 11.7 cubic yards.

How wide should a French drain trench be?

Wide enough to bed the pipe with stone on both sides. Over 150 ft, 8 in wide takes 7.8 tons of stone and 12 in wide 12.1 tons, both at 18 in deep.

How much pipe for a 150 ft French drain?

150 ft of perforated pipe, which is 15 pieces of 10 ft, plus couplers if you use sticks.

Related sizes and guides