Ice and Water Shield Calculator

Enter the length of the eaves, the overhang and the pitch, plus any valleys. You get the width the membrane must reach up the roof, the square feet and the rolls to buy.

Your project

The lower edges of the roof, all the way along.

items

About 10 ft² of membrane each for flashing.

%

Results

Rolls of 200 ft² (36 in × 67 ft)
2 rolls
366 ft² with waste
Membrane needed, with waste
366 ft²
Width up the slope along the eavesFrom the drip edge to 24 in inside the exterior wall line, measured along the roof
3.91 ft
Courses of a 36 in roll across the widthOne course covers 3 ft of the slope, less a 3 in lap
2 courses
Eaves
313 ft²
Valleys (3 ft wide)
0 ft²
  • Ice and water shield is a self-adhering membrane that stops water backing up under shingles at the eaves, in valleys and around penetrations. Many codes require it in cold climates, extending at least 24 inches inside the exterior wall line. Check your local code and the shingle maker, and install it over a clean, dry deck above 40°F, or as the roll instructs.

How this calculator works

The membrane has to run from the lower edge of the roof to a set distance inside the warm wall, measured along the slope. The horizontal distance is the overhang, plus the wall thickness, plus the 24 inches (or 36) inside the wall. Along the roof it is longer by the slope factor, which is √(1 + (pitch ÷ 12)²). Multiply by the eave length. Valleys take a strip about 3 ft wide, and each penetration about 10 ft².

width up the slope = (overhang + wall + inside) ÷ 12 × √(1 + (pitch ÷ 12)²) area = eave length × width

Worked example: 80 ft of eaves with a 12 inch overhang, a 6 inch wall and 24 inches inside, on a 6/12 roof, needs a strip 3.91 ft up the slope: 313 ft². With 2 penetrations and 10% extra that is 366 ft², which is 2 rolls of 200 ft². On a 12/12 roof the width is 4.95 ft, and 30 ft of valley adds 90 ft².

Rolls for the eaves by roof pitch (80 ft of eaves, 12 in overhang, 6 in wall, 24 in inside)

Width up the slope, square feet and rolls.

PitchWidth up the slopeSquare feetRolls
3/123.61 ft2892
4/123.69 ft2952
6/123.91 ft3132
8/124.21 ft3372
10/124.56 ft3643
12/124.95 ft3963

Tips before you buy

  • Check the code: some areas want the membrane 24 inches inside the warm wall, others a certain distance from the eaves, and some need it on low pitches everywhere.
  • Valleys, around chimneys and skylights, and where roofs meet walls are the other places to use it.
  • Roll it onto a clean, dry, smooth deck, starting at the eaves, with laps of 3 to 6 inches as the roll says.
  • Work in the right temperature range. The membrane is hard to stick in the cold and slippery when hot.
  • Lay the membrane over the drip edge at the eaves, and fit the drip edge over the underlayment at the rakes, as the shingle maker shows.

Tools & materials for this project

As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.

Frequently asked questions

How much ice and water shield do I need?

For 80 ft of eaves on a 6/12 roof with a 12 inch overhang, about 366 ft² with 10% extra, which is 2 rolls of 200 ft². Valleys and penetrations are extra.

How far up the roof should ice and water shield go?

Most codes say at least 24 inches inside the exterior wall line, measured along the roof, in cold climates. Some areas ask for 36 inches. Check the local code.

How big is a roll of ice and water shield?

Most rolls are 36 inches wide and about 67 feet long, which is 200 square feet.

Do valleys need ice and water shield?

Yes, usually: a strip about 3 ft wide along the valley. 30 ft of valley adds 90 ft².

Add this calculator to your website

Running a blog, a contractor site or a class page? You can put this calculator on it for free. Copy the code below, and please leave the link underneath the calculator in place. The small script just resizes the frame to fit the results; if your site strips scripts, the calculator still works inside a scrolling frame.

Get the embed code

Related calculators & guides

Estimates only. Results assume standard materials and simple shapes. Supplier products vary, and the final call on quantity, structure and safety is yours. Check your local code and your supplier's guidance before ordering.