Building a Paver Patio: Base Depth, Sand and Materials Needed
Most paver patios that fail do so because of what is underneath, not the pavers themselves. A patio that is laid on a properly compacted 4 to 6 inch crushed-stone base, with a 1 inch bed of sand and a firm edge, will last decades. This guide explains each layer, how deep it should be, and how to order the right amount of each material.
Part of the project planner: Planning a paver patio or garden path.
The layers, from the ground up
- Compacted soil (subgrade). Remove sod and topsoil, which is soft and organic. Dig down to firm soil and compact it. Soft or wet spots should be dug out and filled with stone.
- Geotextile fabric (optional but useful). On clay or soft soil, a fabric layer stops the base stone sinking into the subgrade.
- Base layer. Crushed stone with fines (road base or "crusher run") compacted in lifts. This is the structural layer.
- Bedding sand. A 1 inch screeded layer of coarse concrete sand, which allows the pavers to be set level.
- Pavers. Laid on the sand and tapped into place.
- Edge restraint. Plastic, metal or concrete edging that stops the pavers spreading sideways.
- Joint sand. Swept in to lock the pavers together. Polymeric sand hardens slightly and resists weeds and washout.
How deep should the base be?
- Patios, walkways and pool decks (foot traffic): 4 to 6 inches of compacted base.
- Driveways and areas with vehicles: 8 to 12 inches, in layers, and often more on soft soil.
- Clay soils or places with frost: go to the deeper end of each range, and check what local installers and your supplier recommend. Frost heave is the enemy of pavers.
Install the base in layers ("lifts") of about 4 inches or less, and compact each with a plate compactor. A hand tamper works for very small areas, but is hard work and rarely gives the same density.
How much material do you need?
Take a 12 × 12 ft patio (144 ft²) with a 4 inch base, a 1 inch sand bed, and 6 × 9 in pavers. These are the defaults in the paver calculator:
| Material | How we work it out | Amount |
|---|---|---|
| Pavers (6 × 9 in) | 144 ft² ÷ 0.375 ft² per paver = 384, plus 10% for cuts | 423 pavers |
| Base stone (4 in) | 144 × 4/12 ÷ 27 = 1.78 yd³, plus 20% for compaction | 2.1 yd³, about 3.0 tons |
| Bedding sand (1 in) | 144 × 1/12 ÷ 27 | 0.44 yd³, about 0.6 ton |
| Edge restraint | Perimeter: 2 × (12 + 12) | 48 linear ft |
For a 6 inch base on the same patio, order about 3.2 yd³ (4.5 tons) of stone. The paver count depends on the paver size, with the same 10% for cuts:
| Paver size | Area of one paver | Pavers for 12 × 12 ft |
|---|---|---|
| 4 × 8 in (brick paver) | 0.222 ft² | 713 |
| 6 × 6 in | 0.250 ft² | 634 |
| 6 × 9 in | 0.375 ft² | 423 |
| 12 × 12 in | 1.00 ft² | 159 |
| 16 × 16 in | 1.78 ft² | 90 |
| 24 × 24 in | 4.00 ft² | 40 |
Why the extra 20% on the base? Loose stone compacts as the plate compactor runs over it, so you order more than the finished volume. The sand bed is screeded, not compacted, so it is ordered as is. Use the paver calculator for any other size, and see how many pavers you need for paver counts by patio size.
Step by step
- Plan the layout and slope. Slope the patio away from buildings by about 1/4 inch per foot (about 2%) so water drains. Set string lines at the finished height, and work backward to find the dig depth.
- Dig. Excavate to the depth of base + sand + paver thickness. Call 811 first in the US to find buried lines.
- Compact the subgrade, then add fabric if needed.
- Add and compact the base in layers, wetting it lightly and running over it several times. Check the slope with a level and string.
- Screed the sand. Lay pipes or rails at the right height, pull a straight board across them, and fill and re-screed the low areas. Do not walk on the finished sand.
- Lay the pavers from a corner or a straight edge, working outward and placing them down onto the sand, not sliding them. Stop for any cut pieces and finish them at the end.
- Install the edge restraint and spike it into the base.
- Compact the pavers with a plate compactor fitted with a pad, then sweep joint sand over the surface and compact again. Top up the joints.
Mistakes to avoid
- A shallow or uncompacted base. The number one cause of sinking, rutting and heaving.
- Using stone dust or fine sand as the base. It holds water and shifts. Use an angular, graded stone.
- Too much bedding sand. More than about 1 inch (or using it to level a poor base) means the pavers settle unevenly.
- Skipping the edge restraint. Without it, the pavers at the edge creep outward and the joints open up.
- No slope. Water ponding on or against the house causes damage and ice.
For tons, yards and bags of base by patio size, see how much paver base do I need.
Frequently asked questions
How deep should a paver base be?
4 to 6 inches of compacted crushed stone for patios and walkways, and 8 to 12 inches for driveways. Go to the deeper end on clay or where the ground freezes, and add a 1 inch bed of sand on top.
How much base do I need for a 12 × 12 patio?
At 4 inches deep, about 2.1 cubic yards (about 3.0 tons) of base stone, which includes extra for compaction, plus 0.44 cubic yards of bedding sand. The paver calculator gives the amounts for any size and depth.
Can I lay pavers on sand alone?
Not for a lasting patio. Sand is only the thin bed the pavers sit in. Underneath it you need a compacted layer of angular crushed stone with fines, or the pavers will sink and shift.