How Much Concrete for a 6 Inch Sonotube?

A 6 inch concrete tube filled 4 ft deep holds 0.79 ft³ of concrete exact, before waste. Buy 2 bags of 80 lb mix, which adds 10% for spills and is the figure the calculator below shows. The table covers other heights and several tubes.

Jump to your result ↓

Your project

For a footing, the depth you will fill. For a column, its full height.

tubes
%

Spillage and a hole that is a little oversize.

Results

Example job shown. Change the numbers to match yours.

80 lb bags
2 bags
For the whole job, with waste
What to buy
  • 60 lb bags2 bags
  • 50 lb bags3 bags

Volume

One tube, no waste
0.79 ft³
All tubes, with waste
0.86 ft³
In cubic yards
0.03 yd³
  • Volume is that of a cylinder: π × radius² × height. The form tube diameter is its inside diameter. Footings usually must go below the frost line, and your plans or building department set their size and reinforcement.

Before you buy: round up to whole packs, check the size printed on the label, and add a little spare. Your supplier has the final say.

Blueprint

Ø 6 in4 ft

0.9 ft³ · 2 80 lb bags

Concrete for a 6 inch tube, by height

A 6 in tube is used for small posts and light-duty piers. The "with waste" column adds 10%, and bag counts are for one tube.

HeightOne tubeWith waste80 lb bags60 lb bags50 lb bags
2 ft0.39 ft³0.43 ft³112
3 ft0.59 ft³0.65 ft³222
4 ft0.79 ft³0.86 ft³223
5 ft0.98 ft³1.08 ft³233
6 ft1.18 ft³1.30 ft³334
8 ft1.57 ft³1.73 ft³345

For several tubes (4 ft each)

A deck often needs 4 to 12 footings, so the numbers add up:

Number of tubesConcrete (with waste)Cubic yards80 lb bags
1 tube0.9 ft³0.03 yd³2
4 tubes3.5 ft³0.13 yd³6
6 tubes5.2 ft³0.19 yd³9
9 tubes7.8 ft³0.29 yd³13
12 tubes10.4 ft³0.38 yd³18

Past about 15 to 20 bags, it is worth pricing a small ready-mix delivery. See the concrete bags guide.

Weight and bearing area

A 6 inch tube filled 4 ft deep holds about 118 lb of concrete (150 lb per ft³), which matters if you are moving a precast footing or planning how to pour it. The base of the footing has an area of 0.20 ft², and that is what spreads the load into the soil.

Soil (typical presumptive bearing value)Pounds per ft²Load one footing can bear
Clay or sandy clay1,500295 lb
Sand, silty sand or clayey sand2,000393 lb
Sandy gravel and gravel3,000589 lb

These are the presumptive values used in the International Residential Code for ordinary soils, shown only to illustrate the arithmetic. The footing size for a real deck or building must come from your plans and local code, because the soil, frost depth and loads decide it.

A 6 inch tube: light posts and small piers

A 6 inch tube holds 0.79 cubic feet of concrete per 4 ft of depth, which is 2 bags of 80 lb for one hole with 10% waste. It is the smallest tube size, used for light posts, signs and mailbox posts.

A footing this thin can only carry a small load, so do not use it for a deck. Dig the hole below the frost line for your area to stop frost heave from lifting the post, and put gravel at the bottom for drainage. For a hole this size a post-hole digger does the job, and a hand-mixed batch of bagged concrete is easy to handle.

Want to change anything else? The calculator above is the full Sonotube (Concrete Tube) Calculator: edit any number and the results update instantly.

Tools & materials for this project

Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.

Frequently asked questions

How much concrete in a 6 inch sonotube?

0.20 ft³ for every foot of height. A 4 ft tube holds 0.79 ft³, and with 10% waste you need 2 bags of 80 lb.

How many bags of concrete for a 6 inch tube, 4 feet deep?

2 bags of 80 lb, 2 bags of 60 lb or 3 bags of 50 lb, including 10% waste.

How deep should a 6 inch footing be?

Footings must usually reach below the frost line, and your building plans or local code set the depth and diameter, so use the numbers from your plans.