Concrete needed for a 20 × 24 ft slab, by thickness
These figures are for the whole 480 ft² slab. The last column adds 10% for waste, which is what we suggest you order.
| Thickness | Cubic feet | Cubic yards | 80 lb bags | 60 lb bags | Yards with 10% waste |
|---|---|---|---|---|---|
| 4 in | 160.0 | 5.93 | 267 | 356 | 6.52 |
| 5 in | 200.0 | 7.41 | 334 | 445 | 8.15 |
| 6 in | 240.0 | 8.89 | 400 | 534 | 9.78 |
| 8 in | 320.0 | 11.85 | 534 | 712 | 13.04 |
What a 20 × 24 slab is used for
A 20 × 24 ft slab is a standard two-car garage floor, or a big workshop. Garage slabs are commonly 4 to 6 inches thick (and thicker at the edges), with reinforcement. Follow your plans and local code.
Bags or ready-mix for 20 × 24 ft?
At 6.52 cubic yards, ready-mix is the sensible choice. Doing it with bags would mean 294 bags (about 11.8 tons of dry mix), which is too much to mix by hand before the first batch starts to set. Ask your supplier about their minimum order and how long you have to unload.
Don't forget what goes under and inside it
A slab needs a compacted base, usually 4 inches of gravel, which for this size is about 7.11 cubic yards after allowing for compaction (see the gravel calculator). Reinforcement such as rebar or wire mesh holds cracks tight: the rebar calculator counts bars for a 20 × 24 ft grid.
Base, reinforcement and joints
At 4 inches thick the finished 20 × 24 slab weighs about 12.0 tons. Under it goes a compacted gravel base: 4 inches is about 7.1 yd³ of stone including 20% for compaction (10.0 tons). A grid of #3 rebar at 16 inch centers takes about 39 bars of 20 ft (293 lb).
Concrete cracks as it shrinks, so cut or tool control joints about 8 to 12 ft apart (a common rule is two to three times the slab thickness in inches, read as feet) to decide where. For this slab that means about 1 joint along the 20 ft side and 2 joints along the 24 ft side, cut within 24 hours of the pour.
A 20 × 24 floor, one truck with little margin
At 6 in thick the 480 sq ft floor takes 9.8 cu yd, including 10% waste. A standard mixer truck holds about 10 cu yd, so this fits in one load with only a small margin. A subgrade that is lower in places than you measured can eat that margin quickly, so ask the supplier whether they can add a little extra.
Divide the floor into panels with saw cuts. With two cuts along the 24 ft length (a panel every 8 ft) and one across the 20 ft width (a panel every 10 ft), the result is 6 panels of 80 sq ft each. Make the cuts within about a day of pouring, before shrinkage cracks start to form.
Want to change anything else? The calculator above is the full Concrete Calculator: edit any number and the results update instantly.
Tools & materials for this project
Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.
Frequently asked questions
How many bags of concrete for a 20x24 slab?
For a 4 inch slab you need 267 bags of 80 lb concrete (356 bags of 60 lb), or 294 bags of 80 lb with 10% waste. For a 6 inch slab it is 400 bags of 80 lb, or 440 with 10% waste.
How many cubic yards is a 20x24 slab?
A 20 × 24 ft slab is 5.93 yd³ at 4 inches, 7.41 yd³ at 5 inches and 8.89 yd³ at 6 inches, before waste. Add 5 to 10% when you order.
How much does a 20x24 concrete slab weigh?
At 4 inches thick it weighs roughly 24,000 lb (12.0 tons), at about 150 lb per cubic foot. At 6 inches it is about 36,000 lb.