Concrete needed for a 10 × 10 ft slab, by thickness
These figures are for the whole 100 ft² slab. The last column adds 10% for waste, which is what we suggest you order.
| Thickness | Cubic feet | Cubic yards | 80 lb bags | 60 lb bags | Yards with 10% waste |
|---|---|---|---|---|---|
| 4 in | 33.3 | 1.23 | 56 | 75 | 1.36 |
| 5 in | 41.7 | 1.54 | 70 | 93 | 1.70 |
| 6 in | 50.0 | 1.85 | 84 | 112 | 2.04 |
| 8 in | 66.7 | 2.47 | 112 | 149 | 2.72 |
What a 10 × 10 slab is used for
A 10 × 10 ft slab is a standard patio for a table and four chairs, a floor for a 10 × 10 shed, or the base for a gazebo. Four inches suits a patio or gazebo. A heavily loaded shed or workshop is better at 5 to 6 inches.
Bags or ready-mix for 10 × 10 ft?
At 1.36 cubic yards you are on the border. 62 bags of 80 lb mix is about 2.5 tons of dry material to mix and place before it sets. Many people still do it with a rented mixer and a few helpers, but get a ready-mix quote as well, since delivery fees and short-load charges can make the two options close.
Don't forget what goes under and inside it
A slab needs a compacted base, usually 4 inches of gravel, which for this size is about 1.48 cubic yards after allowing for compaction (see the gravel calculator). Reinforcement such as rebar or wire mesh holds cracks tight: the rebar calculator counts bars for a 10 × 10 ft grid.
Base, reinforcement and joints
At 4 inches thick the finished 10 × 10 slab weighs about 2.5 tons. Under it goes a compacted gravel base: 4 inches is about 1.5 yd³ of stone including 20% for compaction (2.1 tons). A grid of #3 rebar at 16 inch centers takes about 9 bars of 20 ft (68 lb).
Concrete cracks as it shrinks, so cut or tool control joints about 8 to 12 ft apart (a common rule is two to three times the slab thickness in inches, read as feet) to decide where. For this slab that means no joints, as it is small enough to pour as one panel.
Joint layout for a 10 × 10 patio
For a 4 in slab the usual joint spacing is about 8 to 12 ft, and a 10 ft side is inside that, so the 100 sq ft needs no control joint and pours as one panel. If you would still like one, a single cut each way makes four panels of 25 sq ft.
A joint, if you add one, is cut about one quarter of the thickness deep, which is 1 in for a 4 in slab, with a saw the day after the pour or with a groover while the surface is wet. The 1.4 cu yd for the whole patio is about 62 bags if you mix it yourself.
Want to change anything else? The calculator above is the full Concrete Calculator: edit any number and the results update instantly.
Tools & materials for this project
Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.
Frequently asked questions
How many bags of concrete for a 10x10 slab?
For a 4 inch slab you need 56 bags of 80 lb concrete (75 bags of 60 lb), or 62 bags of 80 lb with 10% waste. For a 6 inch slab it is 84 bags of 80 lb, or 92 with 10% waste.
How many cubic yards is a 10x10 slab?
A 10 × 10 ft slab is 1.23 yd³ at 4 inches, 1.54 yd³ at 5 inches and 1.85 yd³ at 6 inches, before waste. Add 5 to 10% when you order.
How much does a 10x10 concrete slab weigh?
At 4 inches thick it weighs roughly 5,000 lb (2.5 tons), at about 150 lb per cubic foot. At 6 inches it is about 7,500 lb.