How Much Concrete for a 16x16 Slab?

A 16 × 16 ft slab (256 ft²) poured 4 inches thick is 3.16 cubic yards exact, before waste (143 bags of 80 lb). Order 3.48 cubic yards of ready-mix or 157 bags of 80 lb mix, which adds 10% for spills and an uneven base. That is the figure the calculator below shows; change the thickness for a 5 or 6 inch slab.

Jump to your result ↓

Your project

Patios, walkways and shed pads are usually 4 in. Driveways are usually 5 to 6 in.

%

Forms flex and subgrades are never perfectly level. 5 to 10% is typical.

Results

Example job shown. Change the numbers to match yours.

Concrete needed
3.48 cubic yards
Includes your waste allowance
What to buy
  • 80 lb bags157 bags
  • 60 lb bags209 bags
  • 40 lb bags313 bags
Ready-mix to orderRounded up to the next ¼ yard. Ask your supplier about short-load fees
3.50 yd³
Cubic feet
93.9 ft³
Cubic meters
2.66 m³
Weight of the concrete neededFor the 3.48 yd³ above, at 150 lb per ft³
14,080 lb
Weight of the ready-mix you orderWhat the truck delivers: the order rounded up to the next ¼ yard, at 150 lb per ft³
14,175 lb
  • Assumptions used: 10% waste added; bag yields of 0.3, 0.45 and 0.6 ft³ for 40, 60 and 80 lb bags; 150 lb per ft³ for the weight.
  • Bag yields used: 0.60 ft³ per 80 lb, 0.45 ft³ per 60 lb, 0.30 ft³ per 40 lb. Check your bag, since brands differ slightly.
  • Ready-mix is usually ordered in ¼ yard steps. Round up rather than down.
  • In metric: an 80 lb bag is about 36 kg, a 60 lb bag about 27 kg and a 40 lb bag about 18 kg.

Before you buy: round up to whole packs, check the size printed on the label, and add a little spare. Your supplier has the final say.

Blueprint

16 ft16 ft4 in157 × 80 lb bags10 of 157 shown

3.48 yd³ · 157 bags

Concrete needed for a 16 × 16 ft slab, by thickness

These figures are for the whole 256 ft² slab. The last column adds 10% for waste, which is what we suggest you order.

ThicknessCubic feetCubic yards80 lb bags60 lb bagsYards with 10% waste
4 in85.33.161431903.48
5 in106.73.951782384.35
6 in128.04.742142855.21
8 in170.76.322853806.95

What a 16 × 16 slab is used for

A 16 × 16 ft slab is a large entertaining patio, a pool deck section, or a floor for a good-sized pavilion or garden room. Four inches for foot traffic, 5 to 6 for anything that carries vehicles or heavy furniture loads.

Bags or ready-mix for 16 × 16 ft?

At 3.48 cubic yards, ready-mix is the sensible choice. Doing it with bags would mean 157 bags (about 6.3 tons of dry mix), which is too much to mix by hand before the first batch starts to set. Ask your supplier about their minimum order and how long you have to unload.

Don't forget what goes under and inside it

A slab needs a compacted base, usually 4 inches of gravel, which for this size is about 3.79 cubic yards after allowing for compaction (see the gravel calculator). Reinforcement such as rebar or wire mesh holds cracks tight: the rebar calculator counts bars for a 16 × 16 ft grid.

Base, reinforcement and joints

At 4 inches thick the finished 16 × 16 slab weighs about 6.4 tons. Under it goes a compacted gravel base: 4 inches is about 3.8 yd³ of stone including 20% for compaction (5.3 tons). A grid of #3 rebar at 16 inch centers takes about 21 bars of 20 ft (158 lb).

Concrete cracks as it shrinks, so cut or tool control joints about 8 to 12 ft apart (a common rule is two to three times the slab thickness in inches, read as feet) to decide where. For this slab that means about 1 joint each way, cut within 24 hours of the pour.

Pouring 256 square feet in one day

At 4 in the 256 sq ft takes 3.5 cu yd, which one truck can deliver in a single load. Suppliers give a set unloading time and charge for extra minutes, so the crew, wheelbarrows, screed and bull float need to be ready before the truck turns into the driveway. Plan on three people, not two.

If a chute cannot reach the whole slab, pour it in two halves of 128 sq ft, finishing one before the other with a form board across the middle. That board sits where a control joint belongs, so the divide costs nothing in appearance.

Want to change anything else? The calculator above is the full Concrete Calculator: edit any number and the results update instantly.

Tools & materials for this project

Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.

Frequently asked questions

How many bags of concrete for a 16x16 slab?

For a 4 inch slab you need 143 bags of 80 lb concrete (190 bags of 60 lb), or 157 bags of 80 lb with 10% waste. For a 6 inch slab it is 214 bags of 80 lb, or 235 with 10% waste.

How many cubic yards is a 16x16 slab?

A 16 × 16 ft slab is 3.16 yd³ at 4 inches, 3.95 yd³ at 5 inches and 4.74 yd³ at 6 inches, before waste. Add 5 to 10% when you order.

How much does a 16x16 concrete slab weigh?

At 4 inches thick it weighs roughly 12,800 lb (6.4 tons), at about 150 lb per cubic foot. At 6 inches it is about 19,200 lb.

Related sizes and guides

Estimates only. Results assume standard materials and simple shapes. Supplier products vary, and the final call on quantity, structure and safety is yours. Check your local code and your supplier's guidance before ordering.