Concrete needed for a 16 × 16 ft slab, by thickness
These figures are for the whole 256 ft² slab. The last column adds 10% for waste, which is what we suggest you order.
| Thickness | Cubic feet | Cubic yards | 80 lb bags | 60 lb bags | Yards with 10% waste |
|---|---|---|---|---|---|
| 4 in | 85.3 | 3.16 | 143 | 190 | 3.48 |
| 5 in | 106.7 | 3.95 | 178 | 238 | 4.35 |
| 6 in | 128.0 | 4.74 | 214 | 285 | 5.21 |
| 8 in | 170.7 | 6.32 | 285 | 380 | 6.95 |
What a 16 × 16 slab is used for
A 16 × 16 ft slab is a large entertaining patio, a pool deck section, or a floor for a good-sized pavilion or garden room. Four inches for foot traffic, 5 to 6 for anything that carries vehicles or heavy furniture loads.
Bags or ready-mix for 16 × 16 ft?
At 3.48 cubic yards, ready-mix is the sensible choice. Doing it with bags would mean 157 bags (about 6.3 tons of dry mix), which is too much to mix by hand before the first batch starts to set. Ask your supplier about their minimum order and how long you have to unload.
Don't forget what goes under and inside it
A slab needs a compacted base, usually 4 inches of gravel, which for this size is about 3.79 cubic yards after allowing for compaction (see the gravel calculator). Reinforcement such as rebar or wire mesh holds cracks tight: the rebar calculator counts bars for a 16 × 16 ft grid.
Base, reinforcement and joints
At 4 inches thick the finished 16 × 16 slab weighs about 6.4 tons. Under it goes a compacted gravel base: 4 inches is about 3.8 yd³ of stone including 20% for compaction (5.3 tons). A grid of #3 rebar at 16 inch centers takes about 21 bars of 20 ft (158 lb).
Concrete cracks as it shrinks, so cut or tool control joints about 8 to 12 ft apart (a common rule is two to three times the slab thickness in inches, read as feet) to decide where. For this slab that means about 1 joint each way, cut within 24 hours of the pour.
Pouring 256 square feet in one day
At 4 in the 256 sq ft takes 3.5 cu yd, which one truck can deliver in a single load. Suppliers give a set unloading time and charge for extra minutes, so the crew, wheelbarrows, screed and bull float need to be ready before the truck turns into the driveway. Plan on three people, not two.
If a chute cannot reach the whole slab, pour it in two halves of 128 sq ft, finishing one before the other with a form board across the middle. That board sits where a control joint belongs, so the divide costs nothing in appearance.
Want to change anything else? The calculator above is the full Concrete Calculator: edit any number and the results update instantly.
Tools & materials for this project
Affiliate links As an Amazon Associate we earn from qualifying purchases. These links do not change what you pay.
Frequently asked questions
How many bags of concrete for a 16x16 slab?
For a 4 inch slab you need 143 bags of 80 lb concrete (190 bags of 60 lb), or 157 bags of 80 lb with 10% waste. For a 6 inch slab it is 214 bags of 80 lb, or 235 with 10% waste.
How many cubic yards is a 16x16 slab?
A 16 × 16 ft slab is 3.16 yd³ at 4 inches, 3.95 yd³ at 5 inches and 4.74 yd³ at 6 inches, before waste. Add 5 to 10% when you order.
How much does a 16x16 concrete slab weigh?
At 4 inches thick it weighs roughly 12,800 lb (6.4 tons), at about 150 lb per cubic foot. At 6 inches it is about 19,200 lb.